It all depends on the type of bathroom remodel you want. What do you envision? If you’re thinking of a quick and easy job, think again. Bathroom remodeling can be an extensive process that takes several weeks, if not months to complete.

There’s also the matter of budget and available resources that will affect how long it’ll take for your contractor to remodel your bathroom:

  • Do you have enough finances? A small bathroom remodel may seem affordable at first but there are other things to consider, such as plumbing changes or increased electrical costs from rewiring old fixtures for new energy-efficient ones. Make sure to ask your contractor beforehand so you know what to expect in terms of the cost before he starts work.
  • What is the contractor’s availability? If you’re remodeling during the busiest season, your contractor may have a backlog and won’t be able to start work for several weeks. Make sure to discuss this with them before you hire them.

Now that you know what goes into bathroom remodeling, how long it takes, and how it can affect your budget, you’re probably wondering what kind of tasks are typically involved in the process? 

Below is a list of some common bathroom remodel tasks:

  • Removal of existing fixtures and tiles
  • Repairing or replacing plumbing and electrical wiring
  • Installation of new fixtures, such as sinks, toilets, bathtubs, and showers
  • Installation or replacement of flooring and wall tiles
  • Painting and wallpapering

How long a bathroom remodel will take depends on how extensive the renovation is. If you’re thinking of only replacing the toilets and floor tiles, your contractor can probably do it in a week or two. On the other hand, if they have to replace all fixtures from the ceiling down to the walls, expect them to work for several months before you can use your new bathroom.

By knowing what tasks are involved in a bathroom remodel and how long it takes about available resources and budget, you’ll be able to plan when hiring a contractor so there won’t be any surprises later on. You also get an idea of whether or not you have enough money allotted for this kind of project. With this information, you’re now ready to take the first step in giving your bathroom a much-needed makeover. Good luck!

Contractors typically work on a bathroom remodel for 2-4 weeks, but this can vary depending on the scope of the project. Typically, more complex projects will take longer. Keep in mind that this is just an average; your contractor may finish sooner or later depending on their availability and the specific tasks involved in your renovation. Be sure to discuss the schedule with them before starting any work.

Efficiently Choosing a Bathroom Remodel Contractor

In the early stages of planning a bathroom remodel, many homeowners may feel that they can do it themselves. While this may be a good idea for some renovations, a bathroom remodel is an involved process and should not be taken lightly. 

It is important to not only use reputable contractors but also to choose bathroom remodel companies with experience in the type of work you need to be done and who will schedule sufficient time for your job.

Demolition 

This step includes removing all fixtures such as toilets, bathtubs, and showers, sinks and vanities, and accessories such as towel bars and mirrors. 

Count on a day to a day and a half of work for this step depending on the size of your bathroom.

Plumbing Rough-In/Demolition

  • Finish Grading – Once all plumbing, electrical, and other rough work have been completed, contractors will need to finish grading the floor so it is level with surrounding surfaces. 
  • Tile Setting – Tiles are set around fixtures such as lavatories, tubs, and showers. 

Count on two days to complete this phase after finishing demolition.

  • Electrical / Wiring – After tile setting, contractors will move on to rough-in electrical wiring which includes outlets and light fixtures above vanities or around mirrors.  Count on one full day for this.

Count on one full day for this step after finishing electrical.

  • Framing – Framing includes cutting studs (vertical support beams) to fit your measurements and nailing the studs into place. They frame out where wallboard, or drywall, will be applied. 

Count on three days of work following the completion of electrical.

  • Wall Insulation – After walls are framed, they finish insulation which includes filling spaces between framing with insulation such as fiberglass batting and sealing it tightly. 

Count on two days for this phase if you do not have any plumbing in the walls that need covering up first. If there is plumbing present in the walls, count on three days.

  • Drywall – The final step in the process includes drywall installation and mud which involves covering up all seams between sheetrock with a special compound called drywall joint compound and sanding it down to create a smooth surface.  Count on two days for this step if there is no plumbing present in the walls and one day if there is plumbing present.
  • Exterior Finish – Exterior finish involves waterproofing the exterior of your bathroom by applying a type of tar tile over siding as well as adding cement board as a backer for tiling.  Count on one day following completion of interior finishing.
  • Sheetrock – Sheetrock wallboard installation follows exterior work which includes cutting, molding, and hanging sheetrock. 

Count on two days for this step.

  • Mudding and Taping – Joint compound is then applied to all seams in the drywall, followed by sanding. 

This phase usually takes two to three days to complete.

  • Paint – After all other work is complete, your contractor will give the bathroom a fresh coat of paint. 

Count on one day for this step.

TOTAL DURATION: 18-21 DAYS This timeframe does not include time for permits, which can take an additional week or two. It is also important to note that these numbers are based on a standard bathroom remodel and may vary depending on the specific needs of your project. For example, adding a standalone shower will add an extra day or two to the overall timeline.

Estimating the Duration of Your Bathroom Renovation Project 

When planning a bathroom remodel, it’s important to keep in mind that the duration of the project can vary depending on several factors. Some of these factors include the size of the bathroom, the scope of the work, and whether any special fixtures or finishes are being installed.

In general, contractors will need approximately 18-21 days to complete a standard bathroom remodel from start to finish. This timeframe does not include time for permits, which can take an additional week or two. 

It is also important to note that these numbers are based on a standard bathroom remodel and may vary depending on the specific needs of your project. For example, adding a standalone shower will add an extra day or two to the overall timeline.

If you’re looking to remodel your bathroom on a budget, there are a few things you can do to speed up the process. For example, you can install basic bathroom fixtures yourself, or choose a contractor who specializes in quick turnaround projects.

No matter what route you choose, it’s important to be aware of the potential delays that can occur during a bathroom renovation. By knowing what to expect, you can plan and avoid any surprises down the road.